Slope Application

- Prepare soil so that area is smooth, and then add fertilizer & lime as required
- Start by stapling the blanket at the top of the slope in a 6" deep x 6" wide (150mm x150mm) trench Backfill and compact trench so that the water will flow evenly onto the blanket
-
- Roll blanket down the slope
- OR horizontally across slopes <50 feet 16m), insuring soil blanket contact
- Overlap adjacent edges of blanket a minimum of 2"(50mm) with parallel blankets
- If more than one blanket is needed for the run then overlap consecutive roll ends a minimum of 4"(100mm) shingle style. Staple overlap areas with staggered pattern with staples