Slope Application

Click on this picture to download Installation Instructions

  1. Prepare soil so that area is smooth, and then add fertilizer & lime as required
  2. Start by stapling the blanket at the top of the slope in a 6" deep x 6" wide (150mm x150mm) trench Backfill and compact trench so that the water will flow evenly onto the blanket
    1. Roll blanket down the slope
    2. OR horizontally across slopes <50 feet 16m), insuring soil blanket contact
  3. Overlap adjacent edges of blanket a minimum of 2"(50mm) with parallel blankets
  4. If more than one blanket is needed for the run then overlap consecutive roll ends a minimum of 4"(100mm) shingle style. Staple overlap areas with staggered pattern with staples

Slope Application

Click on this picture to download Installation Instructions

  1. Prepare soil so that area is smooth, and then add fertilizer & lime as required
  2. Start by stapling the blanket at the top of the slope in a 6" deep x 6" wide (150mm x150mm) trench Backfill and compact trench so that the water will flow evenly onto the blanket
    1. Roll blanket down the slope
    2. OR horizontally across slopes <50 feet 16m), insuring soil blanket contact
  3. Overlap adjacent edges of blanket a minimum of 2"(50mm) with parallel blankets
  4. If more than one blanket is needed for the run then overlap consecutive roll ends a minimum of 4"(100mm) shingle style. Staple overlap areas with staggered pattern with staples